Visually, there isn't much difference this week from last week until you start looking under the covers. The under floor plumbing and other pieces were completed along with getting the inspection passed means that next week the walls start going up. The crawl space beneath the flooring is deeper then I expected so that might provide some uses that I originally didn't think of. The crawl space is fully enclosed by concrete walls and should be a nice dry space.
The crew is doing final prep before installing the plywood floor decking:
It's hard to get a feel of the depth in this picture, but the plumbing and pipes can be seen: