The pace of things have picked up significantly since the arrival of the roof trusses and a lot of activity can be found at the site as well as the ringing of the cash register draining more funds. ^^;
With the trusses up, the crew have started to put up the wall sheathing and roofing. The electrician has been on-site to plan out the rough electrical and soon the plumber will also be out to prepare to do the rough plumbing.
I've been ordering the networking stuff in preparation for running the data/telephone/video wiring which will happen once the electrician and plumber is done and before we put up the drywall.